Closes #205

What

  • Adds D-43 to docs/decisions/scope-process.md, amending D-29 and D-30: milestones R0, R1a, R1b, R2, DR4 and Maintenance replace M1–M5; no due dates; difficulty by label (good first issue = Level 1, help wanted = Level 2, none = core); Atish assigns every ticket.
  • D-29 and D-30 now say "Amended by D-43".
  • Index row, "amended by" marks and next-free line (now D-44) in docs/decisions/README.md.
  • CLAUDE.md "Build schedule" names the new milestones and points to D-43 for what each holds.
  • A22.12 points to D-43 for the milestone split; A22.15's intro notes that HN-0 registers its rows from D-44.
  • docs/architecture/plan.md (A13) gets a "Superseded by D-43" banner; the dated status board itself is unchanged.
  • The Area and Track ticket tables (area-plan.md, track-contract.md, track-ui.md) say that their M-labels are the closed event milestones (added after review).

Split

The R1a/R1b/R2 split is decided, not proposed: it follows the descriptions of the GitHub milestones Atish created on 20 Nov 2026. R1b holds HN-4, HN-7 to HN-11 and HN-16; R2 holds HN-12 to HN-15 and the release 2 part of HN-4b (R-54). The earlier draft of this PR put HN-11 and HN-16 in R2; that was corrected after review.

Not changed: the A22 release contents.

Checks

Docs only. #189, which #205 lists as blocking, is closed as completed (20 Nov 2026). /sx-spec-sync not run.

Closes #205

Co-Authored-By: Claude Sonnet 5.5 <noreply@anthropic.com>
Claude-Session: https://claude.ai/code/session_017Dj9JMHTKZZ4Vn2G9wyGNq

@JoottunAtish JoottunAtish left a comment

Copy link
Copy Markdown
Contributor

Choose a reason for hiding this comment

The reason will be displayed to describe this comment to others. Learn more.

Thanks for picking up #205. This is the right scope, and the D-29/D-30 amendment lines and the D-43 ID are correct (D-43 is free on dev, and no other open PR takes a D- ID). I'm requesting changes for one factual problem, plus a few small fixes.

Blocking: HN-11 and HN-16 belong in R1b, not R2

The milestone split isn't open. It was set on 20 Nov in the GitHub milestones themselves (gh api repos/0ffrian/SphereX/milestones):

  • R1b · First validated hunts: "Rest of A22 release 1: HN-4, HN-7, HN-8, HN-9, HN-10, HN-11, HN-16."
  • R2 · More hunts: "A22 release 2: HN-4b (release 2 part), HN-12, HN-13, HN-14, HN-15."

A22.12 agrees: only HN-12 to HN-15 are labelled release 2. HN-11 (H4 spectra and precovery) and HN-16 (the verified submission routes) are part of R1b's "Done when". So D-43 as written contradicts the decision it says it records ("Decided (Atish, 20 Nov 2026)"). If this merged, anyone reading CLAUDE.md would file HN-11 or HN-16 under R2 and they would drop out of the first validated release.

Please fix it in all four places (inline comments below):

  1. docs/decisions/scope-process.md R1b and R2 rows. Then cut the "Open for Atish" bullet down: the split is decided. Cite the GitHub milestone descriptions as the source.
  2. docs/architecture/discovery-hunts.md "Milestones (D-43)" paragraph. Also drop the "proposed … wait for Atish" sentence.
  3. CLAUDE.md build schedule.
  4. docs/decisions/README.md D-43 index row. Drop "the R1a/R1b split and HN-11, HN-16 placement are proposed".

Non-blocking

  • Milestone names: use the real titles in the D-43 table so people can search GitHub for them: "R0 · Foundations and onboarding", "R1a · Hunts core (minimum)", "R1b · First validated hunts", "R2 · More hunts", "DR4 · Gaia dark companions", "Maintenance".
  • R1a and HN-4b: say "HN-4b (release 1 part)" in R1a, as the milestone does, so R1a and R2 don't both appear to own all of HN-4b. Also, R-27's minimum includes HN-0, which D-43 puts in R0. Word it as "R-27's minimum, except HN-0 (in R0)" or similar.
  • R0: the milestone description is "Licence, the dev branch, HN-0, onboarding docs and the first starter tickets … V6 and the library checks". Not every V check is in R0: #202 (V36) is in R1b. Please mirror the milestone text.
  • One owner per fact: CLAUDE.md repeats the ticket lists and already differs from D-43 (it leaves out HN-0 in R0 and the HN-4b part in R2). I'd prefer CLAUDE.md to name the milestones and point to D-43 for what each one holds.
  • Index size: scope-process.md is now 25,564 bytes, so the index row should say 25 KB, not 24 KB.
  • docs/architecture/plan.md:7 (not in this diff) still says work is tracked as M1 to M5. A one-line "Superseded by D-43 (20 Nov 2026)" pointer would stop agents treating that status board as current.
  • docs/architecture/discovery-hunts.md:1268 (not in this diff) still says the next free IDs are D-42 / Q-485. Since D-43 is now taken, HN-0 (#203) registers the A22 rows from D-44. Worth a note here or in #203.
  • /sx-spec-sync wasn't run. It probably changes nothing here (no section-map or UML impact), but please run it before merge.

CI is green, and the branch merges cleanly into dev.

Comment thread docs/decisions/scope-process.md Outdated
|---|---|
| **R0** | Housekeeping and verification before the build: HN-0, the `V` checks, the library checks, the README and test-helper tickets |
| **R1a** | The release 1 minimum (A22.12, R-27): HN-1, HN-2, HN-3, HN-4b, HN-5, HN-6 |
| **R1b** | The rest of release 1 (R-8): HN-4, HN-7, HN-8, HN-9, HN-10 |

Copy link
Copy Markdown
Contributor

Choose a reason for hiding this comment

The reason will be displayed to describe this comment to others. Learn more.

Blocking. The R1b milestone (set 20 Nov) holds HN-4, HN-7, HN-8, HN-9, HN-10, HN-11 and HN-16. Suggest:

| **R1b · First validated hunts** | The rest of release 1 (R-8): HN-4, HN-7, HN-8, HN-9, HN-10, HN-11, HN-16 |

Comment thread docs/decisions/scope-process.md Outdated
| **R0** | Housekeeping and verification before the build: HN-0, the `V` checks, the library checks, the README and test-helper tickets |
| **R1a** | The release 1 minimum (A22.12, R-27): HN-1, HN-2, HN-3, HN-4b, HN-5, HN-6 |
| **R1b** | The rest of release 1 (R-8): HN-4, HN-7, HN-8, HN-9, HN-10 |
| **R2** | Release 2: HN-11 to HN-16, and the release 2 part of HN-4b (R-54) |

Copy link
Copy Markdown
Contributor

Choose a reason for hiding this comment

The reason will be displayed to describe this comment to others. Learn more.

Blocking. R2 holds only HN-12 to HN-15 and the release 2 part of HN-4b. A22.12 labels only those as release 2. Suggest:

| **R2 · More hunts** | Release 2: HN-12, HN-13, HN-14, HN-15, and the release 2 part of HN-4b (R-54) |

Comment thread docs/decisions/scope-process.md Outdated
| Milestone | Holds |
|---|---|
| **R0** | Housekeeping and verification before the build: HN-0, the `V` checks, the library checks, the README and test-helper tickets |
| **R1a** | The release 1 minimum (A22.12, R-27): HN-1, HN-2, HN-3, HN-4b, HN-5, HN-6 |

Copy link
Copy Markdown
Contributor

Choose a reason for hiding this comment

The reason will be displayed to describe this comment to others. Learn more.

Nit: say "HN-4b (release 1 part)" here, as the milestone does. Otherwise R1a and R2 both appear to own HN-4b. R-27's minimum also includes HN-0, which is in R0, so "R-27's minimum, except HN-0 (R0)" is more accurate.

Comment thread docs/decisions/scope-process.md Outdated

| Milestone | Holds |
|---|---|
| **R0** | Housekeeping and verification before the build: HN-0, the `V` checks, the library checks, the README and test-helper tickets |

Copy link
Copy Markdown
Contributor

Choose a reason for hiding this comment

The reason will be displayed to describe this comment to others. Learn more.

Nit: not every V check is in R0. #202 (V36) is in R1b, next to the ticket it blocks. Please mirror the milestone description: "Licence, the dev branch, HN-0, onboarding docs and the first starter tickets; V6 and the library checks."

Comment thread docs/decisions/scope-process.md Outdated
- **Difficulty is a label, not a milestone:** `good first issue` is Level 1, `help wanted` is Level 2, and a ticket with neither is core work. Atish assigns every ticket (D-17).
- **Unchanged:** the contents of the A22 releases. D-43 only names where each ticket is tracked.
- **Why:** M1 to M5 were the event's independent tracks, due 8 to 15 Nov. The event build is done, and the Discovery hunts ship in releases that overlap, so the old names and due dates no longer describe the work.
- **Open for Atish:** the A22.12 text does not define R1a and R1b. The split above follows "Release 1 minimum" (R1a) and issue #202 ("R1b: blocks HN-4"). Placing HN-11 and HN-16 in R2 is also proposed: A22.12 does not label them.

Copy link
Copy Markdown
Contributor

Choose a reason for hiding this comment

The reason will be displayed to describe this comment to others. Learn more.

Blocking (follows from the rows above). The split isn't open: the GitHub milestone descriptions, created by Atish on 20 Nov, define R1a, R1b and R2 ticket by ticket. Please replace this bullet with a Source: line citing those descriptions, and drop the "proposed" wording.

Comment thread docs/architecture/discovery-hunts.md Outdated
| **HN-17** | H10 cross-match on Gaia DR4 | HN-1; DR4 | Kevin |
| Later | Watch saved objects; sharing squares between PCs; replay with hunts | | |

**Milestones (D-43).** Tickets are tracked under release milestones: **R0** (HN-0 and the housekeeping and verification tickets), **R1a** (the release 1 minimum: HN-1, HN-2, HN-3, HN-4b, HN-5, HN-6), **R1b** (the rest of release 1: HN-4, HN-7, HN-8, HN-9, HN-10), **R2** (HN-11 to HN-16, and the release 2 part of HN-4b), **DR4** (HN-17, when Gaia DR4 is out) and **Maintenance** (standing, outside the hunts). The R1a/R1b split and the placing of HN-11 and HN-16 are proposed in D-43 and wait for Atish.

Copy link
Copy Markdown
Contributor

Choose a reason for hiding this comment

The reason will be displayed to describe this comment to others. Learn more.

Blocking. Same fix as in D-43: R1b is HN-4, HN-7 to HN-11 and HN-16; R2 is HN-12 to HN-15 plus the release 2 part of HN-4b. Please also drop the last sentence ("proposed in D-43 and wait for Atish"). Better still, keep this to a pointer ("tracked under the release milestones of D-43") so the mapping lives only in D-43.

Comment thread CLAUDE.md Outdated
## Build schedule

The team builds from 5 Nov 2026 (decisions D-14), setting aside the event rule against building before 14 Nov. Work is tracked in the GitHub project "SphereX and PlanetX - NASA COMPETITION 2026" as milestones M1–M5 (D-29). M1–M4 build against fixtures and do not depend on each other; only M5 integrates them.
The team builds from 5 Nov 2026 (decisions D-14), setting aside the event rule against building before 14 Nov. Work is tracked in the GitHub project "SphereX and PlanetX - NASA COMPETITION 2026" under release milestones (D-43, which amends D-29 and D-30; M1–M5 are closed): **R0** (housekeeping and verification), **R1a** (the release 1 minimum: HN-1, HN-2, HN-3, HN-4b, HN-5, HN-6), **R1b** (the rest of release 1: HN-4, HN-7 to HN-10), **R2** (HN-11 to HN-16), **DR4** (HN-17, ships when Gaia DR4 is out) and **Maintenance** (standing, app fixes outside the hunts). No due dates for now. Difficulty is a label: `good first issue` is Level 1, `help wanted` is Level 2, no label is core work. Atish assigns every ticket.

Copy link
Copy Markdown
Contributor

Choose a reason for hiding this comment

The reason will be displayed to describe this comment to others. Learn more.

Blocking. Every agent loads CLAUDE.md, so a wrong mapping here does the most damage. HN-11 and HN-16 are in R1b, not R2. This list also already differs from D-43 (no HN-0 in R0, no HN-4b part in R2). Suggest dropping the ticket lists and naming the milestones only, e.g. "…under the release milestones R0, R1a, R1b, R2, DR4 and Maintenance (D-43 lists what each holds; it amends D-29 and D-30, and M1–M5 are closed)."

Comment thread docs/decisions/README.md Outdated
| D-40 | Issue #93: engine speed, seeded patterns, physics corrections and new card fields | Decided (Atish, 11 Nov 2026); built except Q-361; Q-346 built by Q-385; performance waves Q-381 to Q-387 | [rendering-engines-tuning](rendering-engines-tuning.md#d-40-issue-93-engine-speed-seeded-patterns-physics-corrections-and-new-card-fields-decided-by-atish-11-nov-2026) |
| D-41 | Project licence: BSD-3-Clause for code and mock-ups, CC-BY-4.0 for docs; data and third-party parts keep their terms (their licence table comes with #200); GPL only as an optional plugin the user installs | Decided (Atish, 24 Nov 2026, PR #212); Space Apps terms checked 24 Nov 2026 | [scope-process](scope-process.md#d-41-project-licence) |
| D-42 | `dev` is the development branch: all work branches off `dev` and merges back into it by PR; `main` is frozen at `b7b4a1d6` and `dev` is the default branch | Decided (Atish, 20 Nov 2026); GitHub settings to apply | [scope-process](scope-process.md#d-42-dev-is-the-development-branch-main-is-frozen) |
| D-43 | Release milestones R0, R1a, R1b, R2, DR4 and Maintenance replace M1 to M5; difficulty by label; Atish assigns every ticket | Decided (Atish, 20 Nov 2026); the R1a/R1b split and HN-11, HN-16 placement are proposed | [scope-process](scope-process.md#d-43-release-milestones-replace-m1-to-m5) |

Copy link
Copy Markdown
Contributor

Choose a reason for hiding this comment

The reason will be displayed to describe this comment to others. Learn more.

Blocking. Drop "the R1a/R1b split and HN-11, HN-16 placement are proposed": both were decided with the milestones on 20 Nov. Status: Decided (Atish, 20 Nov 2026).

Comment thread docs/decisions/README.md Outdated
| File | Holds | Size |
|---|---|---|
| [scope-process.md](scope-process.md) | scope cuts, doc layout, owners, build dates, milestones, the post-event backlog, the demo object and data release, ID reservations | 8 D, 13 Q, 23 KB |
| [scope-process.md](scope-process.md) | scope cuts, doc layout, owners, build dates, milestones, the post-event backlog, the demo object and data release, ID reservations | 9 D, 13 Q, 24 KB |

Copy link
Copy Markdown
Contributor

Choose a reason for hiding this comment

The reason will be displayed to describe this comment to others. Learn more.

Nit: scope-process.md is 25,564 bytes on this branch, so 25 KB.

HN-11 and HN-16 move to R1b as in the GitHub milestones; real milestone
titles; CLAUDE.md and A22.12 point to D-43; plan.md and the A22.15 next-free
note get pointers.

Co-Authored-By: Claude Sonnet 5.5 <noreply@anthropic.com>
Claude-Session: https://claude.ai/code/session_017Dj9JMHTKZZ4Vn2G9wyGNq

@JoottunAtish JoottunAtish left a comment

Copy link
Copy Markdown
Contributor

Choose a reason for hiding this comment

The reason will be displayed to describe this comment to others. Learn more.

Re-reviewed at 29096d4. Every point from the first review is addressed:

  • Blocking, fixed: R1b now holds HN-4, HN-7 to HN-11 and HN-16, and R2 holds HN-12 to HN-15 plus the release 2 part of HN-4b. This matches the GitHub milestone descriptions and A22.12. The "Open for Atish" bullet is now a Source: line, and the "proposed" wording is gone from the index row and from A22.12.
  • CLAUDE.md and A22.12 now just name the milestones and point to D-43, so the ticket lists live in one place.
  • The milestone titles match GitHub. R1a says "HN-4b (release 1 part)" and leaves out HN-0, and R0 mirrors its milestone description. The V36/#202 exception is noted.
  • The index size is 25 KB, plan.md A13 has a superseded-by-D-43 pointer, and A22.15 notes that HN-0 registers its rows from D-44.

The section links resolve (#d-43-release-milestones-replace-m1-to-m5, #a2212-plan-tickets-and-owners). D-43 is still free on dev, and the next-free line (D-44 / Q-487) is correct. Approved.

@KevinYerkiah KevinYerkiah left a comment

Copy link
Copy Markdown
Collaborator

Choose a reason for hiding this comment

The reason will be displayed to describe this comment to others. Learn more.

Approving. Docs-only, scope matches #205, D-43 is free on dev, and the index row, the "Amended by D-43" lines on D-29 and D-30, and the next-free line (D-44, Q-487) are consistent. No blocking issues. Non-blocking comments:

  1. "Proposed" marking missing. The PR body says D-43 marks the R1a/R1b split and the HN-11/HN-16 placement as proposed. The diff (docs/decisions/scope-process.md and the index row) says flatly "Decided (Atish, 20 Nov 2026)". Either mark the split as proposed, or say Atish confirmed it.
  2. Body contradicts the table. The body puts HN-11 and HN-16 in R2. The D-43 table puts them in R1b; R2 holds only HN-12 to HN-15 and the HN-4b release-2 part. Fix one of them.
  3. Body understates the change. It says docs/architecture/plan.md is not changed, but the diff adds a "Superseded by D-43" banner to A13 there.
  4. #189. The body says "Blocked by #189". Please confirm it is merged or irrelevant before merging.
  5. Sweep not done. /sx-spec-sync was not run, and docs/architecture/moving-objects/ (A16.7, A19.14) may still place tickets in M4/M5. Good-to-have before R1a starts: point those at the D-43 milestones.

Generated by Claude Code

… are closed milestones (D-43)

Co-Authored-By: Claude Sonnet 5.5 <noreply@anthropic.com>
Claude-Session: https://claude.ai/code/session_017Dj9JL8HPhcxQHyG7e9ABN
Sign up for free to join this conversation on GitHub. Already have an account? Sign in to comment

Labels

None yet

Projects

None yet

Development

Successfully merging this pull request may close these issues.

Record D-43: release milestones replace M1–M5

4 participants