flowchart TD
%% Phases
subgraph BD [Business Development & Tendering]
O[Opportunity Identified] --> T[Tender Decision]
T --> E[Estimation & BOQ Pricing]
E --> S[Bid Submission]
S --> A{Awarded?}
end
subgraph PRE [Pre-Construction]
A -->|Yes| C[Contract Signing]
C --> P[Project Setup]
P --> B[Budget & Cost Codes Baseline]
B --> SCH[Schedule & Resource Plan]
end
subgraph EXEC [Execution & Control]
SCH --> PR[Procurement & Subcontracts]
SCH --> MOB[Site Mobilization]
PR --> EXEC_W[Work Execution]
MOB --> EXEC_W
EXEC_W --> DSR[Daily Site Reports & Progress]
end
subgraph COMM [Commercial & Financial]
DSR --> M[Measurement & Valuation]
M --> CERT[Payment Certification]
CERT --> INV[Client Invoicing / eTIMS]
INV --> COLL[Cash Collection]
DSR --> VAR[Variation Management]
VAR --> M
end
subgraph CLOSE [Closeout]
COLL --> PC[Practical Completion]
PC --> HO[Handover]
HO --> DLP[Defects Liability Period]
DLP --> FC[Final Certificate & Retention Release]
end
sequenceDiagram
participant Site as Site / Storekeeper
participant PM as Project Manager
participant Proc as Procurement
participant Fin as Finance / AP
participant Vendor as Supplier
Site->>PM: 1. Raise Purchase Requisition (PR)
PM->>Proc: 2. Approve PR (Budget Check)
Proc->>Vendor: 3. Request for Quotation (RFQ)
Vendor-->>Proc: 4. Submit Quotes
Proc->>PM: 5. Quote Evaluation & Recommendation
PM->>Fin: 6. Request PO Approval
Fin->>Vendor: 7. Issue Purchase Order (PO) (Commits Cost)
Vendor-->>Site: 8. Deliver Materials + Delivery Note
Site->>Proc: 9. Goods Received Note (GRN) & QA Check
Vendor-->>Fin: 10. Submit Invoice + eTIMS
Fin->>Fin: 11. Three-Way Match (PO + GRN + Invoice)
Fin->>Vendor: 12. Process Payment & Post to GL
Note over Site, Fin: -- Material Consumption Flow --
Site->>Site: 13. Material Issue to Site / Work Package
Site->>Fin: 14. Consumption Record
Fin->>Fin: 15. Auto-Post: Debit Job Cost, Credit Inventory
stateDiagram-v2
[*] --> WorkExecuted
WorkExecuted --> Measured: Joint Measurement (QS)
Measured --> Valuation: Consultant Valuation
Valuation --> Certified: Payment Certificate Issued
state Certified {
[*] --> GrossValue
GrossValue --> LessRetention
LessRetention --> LessAdvance
LessAdvance --> AddVAT
AddVAT --> LessWHT
LessWHT --> NetPayable
}
Certified --> Invoiced: ERP Generates Invoice + eTIMS
Invoiced --> AccountsReceivable: Recognize Revenue & Debt
AccountsReceivable --> Collected: Cash Receipt
Collected --> [*]
flowchart TD
subgraph Pre-Award
PQ[Prequalification / NCA Check] --> RFQ[Subcontract RFQ]
RFQ --> EVAL[Commercial & Technical Eval]
EVAL --> AWD[Subcontract Award]
end
subgraph Execution
AWD --> SC_Setup[Create Subcontract Commitment]
SC_Setup --> WRK[Work Execution]
WRK --> MEAS[Joint Measurement]
end
subgraph Payment Cycle
MEAS --> APP[Subcontractor Payment App]
APP --> QS_REV[QS Review & Validation]
QS_REV --> CERT[Issue Subcontract Certificate]
CERT --> DED[Deduct Retention & WHT]
DED --> AP[Accounts Payable]
AP --> PAY[Payment Processing]
end
flowchart LR
A((Start: Issue/RFI)) --> B[Identify Potential Variation]
B --> C{Client Driven or Site Driven?}
C -->|Client| D[Receive Site Instruction]
C -->|Site| E[Raise RFI/Notification]
D --> F[Prepare Cost & Time Estimate]
E --> F
F --> G[Submit Variation Quotation]
G --> H{Approved by Client?}
H -->|No| I[Revise or Reject]
H -->|Yes| J[Update Contract Value]
J --> K[Update Project Budget]
K --> L[Execute Works]
L --> M((End: Bill Variation))
sequenceDiagram
participant Emp as Employee / Worker
participant Site as Site Supervisor
participant HR as HR / Payroll
participant Fin as Finance
participant KRA as Statutory (KRA/NSSF/SHIF)
Emp->>Site: 1. Biometric Clock-In / Attendance
Site->>Site: 2. Assign to Cost Code / Task
Site->>HR: 3. Approve Weekly/Monthly Timesheet
HR->>HR: 4. Calculate Gross Pay
HR->>HR: 5. Calculate Deductions (PAYE, SHIF, NSSF, AHL)
HR->>Fin: 6. Finalize Payroll Run
Fin->>Fin: 7. Allocate Labour Cost to Project Ledger
Fin->>Emp: 8. Disburse Net Pay
Fin->>KRA: 9. Remit Statutory Deductions (by 9th)