Construction Business Management & ERP System — Process Models

1. End-to-End Project Lifecycle (High-Level)

flowchart TD
    %% Phases
    subgraph BD [Business Development & Tendering]
        O[Opportunity Identified] --> T[Tender Decision]
        T --> E[Estimation & BOQ Pricing]
        E --> S[Bid Submission]
        S --> A{Awarded?}
    end

    subgraph PRE [Pre-Construction]
        A -->|Yes| C[Contract Signing]
        C --> P[Project Setup]
        P --> B[Budget & Cost Codes Baseline]
        B --> SCH[Schedule & Resource Plan]
    end

    subgraph EXEC [Execution & Control]
        SCH --> PR[Procurement & Subcontracts]
        SCH --> MOB[Site Mobilization]
        PR --> EXEC_W[Work Execution]
        MOB --> EXEC_W
        EXEC_W --> DSR[Daily Site Reports & Progress]
    end

    subgraph COMM [Commercial & Financial]
        DSR --> M[Measurement & Valuation]
        M --> CERT[Payment Certification]
        CERT --> INV[Client Invoicing / eTIMS]
        INV --> COLL[Cash Collection]
        
        DSR --> VAR[Variation Management]
        VAR --> M
    end

    subgraph CLOSE [Closeout]
        COLL --> PC[Practical Completion]
        PC --> HO[Handover]
        HO --> DLP[Defects Liability Period]
        DLP --> FC[Final Certificate & Retention Release]
    end
Loading

2. Procure-to-Pay (Material Purchase & Consumption)

sequenceDiagram
    participant Site as Site / Storekeeper
    participant PM as Project Manager
    participant Proc as Procurement
    participant Fin as Finance / AP
    participant Vendor as Supplier

    Site->>PM: 1. Raise Purchase Requisition (PR)
    PM->>Proc: 2. Approve PR (Budget Check)
    Proc->>Vendor: 3. Request for Quotation (RFQ)
    Vendor-->>Proc: 4. Submit Quotes
    Proc->>PM: 5. Quote Evaluation & Recommendation
    PM->>Fin: 6. Request PO Approval
    Fin->>Vendor: 7. Issue Purchase Order (PO) (Commits Cost)
    Vendor-->>Site: 8. Deliver Materials + Delivery Note
    Site->>Proc: 9. Goods Received Note (GRN) & QA Check
    Vendor-->>Fin: 10. Submit Invoice + eTIMS
    Fin->>Fin: 11. Three-Way Match (PO + GRN + Invoice)
    Fin->>Vendor: 12. Process Payment & Post to GL

    Note over Site, Fin: -- Material Consumption Flow --
    Site->>Site: 13. Material Issue to Site / Work Package
    Site->>Fin: 14. Consumption Record
    Fin->>Fin: 15. Auto-Post: Debit Job Cost, Credit Inventory
Loading

3. Client Billing to Cash (Order-to-Cash)

stateDiagram-v2
    [*] --> WorkExecuted
    WorkExecuted --> Measured: Joint Measurement (QS)
    Measured --> Valuation: Consultant Valuation
    Valuation --> Certified: Payment Certificate Issued
    
    state Certified {
        [*] --> GrossValue
        GrossValue --> LessRetention
        LessRetention --> LessAdvance
        LessAdvance --> AddVAT
        AddVAT --> LessWHT
        LessWHT --> NetPayable
    }
    
    Certified --> Invoiced: ERP Generates Invoice + eTIMS
    Invoiced --> AccountsReceivable: Recognize Revenue & Debt
    AccountsReceivable --> Collected: Cash Receipt
    Collected --> [*]
Loading

4. Subcontractor Management

flowchart TD
    subgraph Pre-Award
        PQ[Prequalification / NCA Check] --> RFQ[Subcontract RFQ]
        RFQ --> EVAL[Commercial & Technical Eval]
        EVAL --> AWD[Subcontract Award]
    end

    subgraph Execution
        AWD --> SC_Setup[Create Subcontract Commitment]
        SC_Setup --> WRK[Work Execution]
        WRK --> MEAS[Joint Measurement]
    end

    subgraph Payment Cycle
        MEAS --> APP[Subcontractor Payment App]
        APP --> QS_REV[QS Review & Validation]
        QS_REV --> CERT[Issue Subcontract Certificate]
        CERT --> DED[Deduct Retention & WHT]
        DED --> AP[Accounts Payable]
        AP --> PAY[Payment Processing]
    end
Loading

5. Variation & Change Order Workflow

flowchart LR
    A((Start: Issue/RFI)) --> B[Identify Potential Variation]
    B --> C{Client Driven or Site Driven?}
    C -->|Client| D[Receive Site Instruction]
    C -->|Site| E[Raise RFI/Notification]
    D --> F[Prepare Cost & Time Estimate]
    E --> F
    F --> G[Submit Variation Quotation]
    G --> H{Approved by Client?}
    H -->|No| I[Revise or Reject]
    H -->|Yes| J[Update Contract Value]
    J --> K[Update Project Budget]
    K --> L[Execute Works]
    L --> M((End: Bill Variation))
Loading

6. Labour & Payroll (Direct Project Staff)

sequenceDiagram
    participant Emp as Employee / Worker
    participant Site as Site Supervisor
    participant HR as HR / Payroll
    participant Fin as Finance
    participant KRA as Statutory (KRA/NSSF/SHIF)

    Emp->>Site: 1. Biometric Clock-In / Attendance
    Site->>Site: 2. Assign to Cost Code / Task
    Site->>HR: 3. Approve Weekly/Monthly Timesheet
    HR->>HR: 4. Calculate Gross Pay
    HR->>HR: 5. Calculate Deductions (PAYE, SHIF, NSSF, AHL)
    HR->>Fin: 6. Finalize Payroll Run
    Fin->>Fin: 7. Allocate Labour Cost to Project Ledger
    Fin->>Emp: 8. Disburse Net Pay
    Fin->>KRA: 9. Remit Statutory Deductions (by 9th)