Node Evaluation Process

The Core Formula: f(n) = g(n) + h(n)

Components Breakdown

  • g(n): Actual cost from start to node n
  • h(n): Heuristic estimate from node n to goal
  • f(n): Total estimated cost of path through n

Step-by-Step Evaluation

Example Setup

Grid with costs:
┌─┬─┬─┬─┬─┐
│ │ │ │G│ │  S = Start (0,2)
├─┼─┼─┼─┼─┤  G = Goal (3,0)
│ │ │█│ │ │  █ = Obstacle
├─┼─┼─┼─┼─┤  Numbers = step order
│S│1│2│3│ │
└─┴─┴─┴─┴─┘

Step 1: Initialize Start Node

Node S (0,2):
g(S) = 0           (distance from start)
h(S) = 5           (Manhattan to goal: |3-0| + |0-2|)
f(S) = 0 + 5 = 5   (total estimated cost)

Step 2: Evaluate Neighbors

Node 1 (1,2)

g(1) = g(S) + 1 = 0 + 1 = 1    (cost to reach)
h(1) = |3-1| + |0-2| = 4       (heuristic to goal)
f(1) = 1 + 4 = 5               (total estimate)
parent(1) = S                   (for path reconstruction)

Node Up (0,1)

g(up) = g(S) + 1 = 1
h(up) = |3-0| + |0-1| = 4
f(up) = 1 + 4 = 5
parent(up) = S

Node Down (0,3) - Out of bounds, skip

Step 3: Select Best Node

Open Set: {Node1(f=5), NodeUp(f=5)}
Both have same f-cost, choose Node1 (arbitrary tie-breaking)
Current = Node1
Move Node1 from Open to Closed set

Step 4: Expand Node 1

Node 2 (2,2)

g(2) = g(1) + 1 = 2
h(2) = |3-2| + |0-2| = 3
f(2) = 2 + 3 = 5
parent(2) = Node1

Node (1,1)

g(1,1) = g(1) + 1 = 2
h(1,1) = |3-1| + |0-1| = 3
f(1,1) = 2 + 3 = 5
parent(1,1) = Node1

Complete Evaluation Table

Node g(n) h(n) f(n) Parent Status
S(0,2) 0 5 5 null Closed
(1,2) 1 4 5 S Closed
(0,1) 1 4 5 S Open
(2,2) 2 3 5 (1,2) Open
(1,1) 2 3 5 (1,2) Open
(3,2) 3 2 5 (2,2) Open
(2,1) 3 2 5 (1,1) Open
(3,1) 4 1 5 (3,2) Open
(3,0) 5 0 5 (3,1) GOAL

Key Insights

1. Consistent f-values

Notice all nodes have f(n) = 5, indicating optimal heuristic!

2. Path Reconstruction

Goal(3,0) ← (3,1) ← (3,2) ← (2,2) ← (1,2) ← Start(0,2)
Final path: S → 1 → 2 → 3 → G
Total cost: 5 (matches our estimate!)

3. Tie-Breaking Strategies

When f-values are equal:

  • Prefer lower h-value: Closer to goal
  • Prefer higher g-value: Further from start
  • LIFO: Last In, First Out
  • Coordinate-based: Consistent ordering

Implementation Details

class Node {
    constructor(x, y) {
        this.x = x;
        this.y = y;
        this.gCost = Infinity;
        this.hCost = 0;
        this.parent = null;
    }
    
    get fCost() {
        return this.gCost + this.hCost;
    }
    
    calculateHeuristic(goal) {
        // Manhattan distance
        this.hCost = Math.abs(this.x - goal.x) + Math.abs(this.y - goal.y);
    }
    
    updateCosts(parent, goal) {
        this.gCost = parent.gCost + this.getMoveCost(parent);
        this.calculateHeuristic(goal);
        this.parent = parent;
    }
    
    getMoveCost(parent) {
        // Diagonal movement costs √2, cardinal costs 1
        const dx = Math.abs(this.x - parent.x);
        const dy = Math.abs(this.y - parent.y);
        return (dx === 1 && dy === 1) ? Math.sqrt(2) : 1;
    }
}

Common Mistakes

1. Forgetting to Update g-cost

// WRONG: Only checking if node is in closed set
if (!closedSet.has(neighbor)) {
    openSet.add(neighbor);
}

// CORRECT: Check if new path is better
const tentativeG = current.gCost + moveCost;
if (tentativeG < neighbor.gCost) {
    neighbor.updateCosts(current, goal);
    openSet.add(neighbor);
}

2. Incorrect Heuristic Calculation

// WRONG: Using Euclidean for 4-directional movement
h = Math.sqrt(dx*dx + dy*dy);

// CORRECT: Using Manhattan for 4-directional
h = Math.abs(dx) + Math.abs(dy);

3. Not Handling Ties

// WRONG: Arbitrary selection
let current = openSet.values().next().value;

// BETTER: Consistent tie-breaking
let current = Array.from(openSet).reduce((best, node) => {
    if (node.fCost < best.fCost) return node;
    if (node.fCost === best.fCost && node.hCost < best.hCost) return node;
    return best;
});

Previous: Heuristic Mathematics Next: Open/Closed Set Management